Item 1

Data center development standards

Would double the data center setback from 500 to 1,000 feet and require notice to property owners and registered associations within half a mile of the site.

City documents

Proposal excerpt · pp. 4–11 (PDF) · City packet · pp. 4–11 (PDF)

How close could a data center be, and who would hear about it?

The Board would set rules for future data centers in the City’s three industrial zoning districts. The packet names no site or applicant. A developer would still need a Planning Commission hearing and Board approval of its plan before receiving a building permit.

Proposal history

What earlier documents say

In October, the Board required a 500-foot setback from every property line for data centers. The ordinance also requires utility-capacity letters and Board approval of a development plan before a building permit.

What is proposed for December 1

The draft doubles the setback to 1,000 feet and adds notice to property owners and registered associations within half a mile. This vote sets standards for future applications.

Questions and evidence

What the records tell us

Which facilities would these rules cover?

Readers new to the issue

The City’s 2023 zoning materials describe buildings or dedicated spaces that house large groups of computers to store, process or distribute data. Examples include weather modeling and cryptocurrency mining. The December draft sets development standards for data centers in the I-1, I-2 and I-3 industrial districts.

Source · p. 4 · p. 8 · City’s October 2023 definition and examples, page 45

Who would receive notice of a proposed site?

Nearby owners and renters

The draft calls for notice to owners of parcels within half a mile of the site boundaries and to homeowner, neighborhood and merchants associations in that area registered with Planning and Zoning. It does not require individual notices to renters. Once a site is proposed, Planning’s parcel and association lists would show who should receive notice.

Source · p. 8 · p. 11 · City Planning and address-based zoning lookup

When could the operator test generators, and how would it check noise?

Neighbors within earshot

Routine tests would run on weekdays from 10 a.m. to 4 p.m., excluding state and federal holidays. The operator would post the schedule online and give owners within 1,000 feet at least 24 hours’ written notice. A third party would study noise before the building permit. A second study after construction would include backup power in operation. Both studies must show compliance with the City’s noise code (§ 16-45).

Source · p. 9

Who would check whether the power supply can serve existing customers?

Electric customers

If a public or franchise utility would supply all the power, it would certify that it can serve the project without harming other customers and identify whether required upgrades have gone before the Arkansas Public Service Commission. A fully independent system would need a study showing it can meet the project’s demand. A mixed system would need both utility certification and a study of effects on other customers.

Source · p. 9 · p. 10

What would the developer have to show about cooling and water?

Water customers and well owners

The draft permits air cooling, efficient closed-loop liquid cooling or equivalent technology. It prohibits once-through and open-loop cooling, and evaporative-only cooling that uses drinking water as its primary cooling medium. Applicants must estimate normal-day, peak-day and annual use. City-served applicants must document current and future capacity for existing customers as well as the project. Nonpublic groundwater use or any surface-water withdrawal for cooling would require a study of supply and effects on wells and water sources.

Source · p. 9 · p. 10

Where could a neighbor report a noise problem?

Neighbors and City inspectors

The operator would have to name a community contact on its website and give Planning an on-call contact. A neighbor could record the date and time of the disturbance, compare it with the posted generator schedule and request the acoustic studies. The draft sets no deadline for answering a complaint.

Source · p. 8 · p. 9

What did the commission vote on, and who would decide a future project?

Directors and meeting attendees

On November 10 the commission recommended the proposed rules by a 7–0 vote. For a later project, the draft calls for the Board to consider the commission’s recommendation at its second regular meeting after commission action. The Board could approve, amend or deny the plan, send specific questions back, or continue the item to a stated date.

Source · p. 7 · p. 11

Still to confirm

What goes to the Board if the Planning Commission makes no recommendation?

Applicants and meeting attendees

Page 11 says the application goes to the Board. The same clause treats the commission’s inaction as a recommendation to deny and says the application goes forward with no recommendation. Ask Planning which recommendation would appear in the Board packet and check the wording the Board adopts.

Source · p. 11

The marked-up setback rule

In § 27-709-3(A), Planning strikes out 500 feet and inserts 1,000. Farther down, the marked text introduces a community contact. The detailed utility requirements continue on pages 9–10.

City packet · p. 8 (PDF)

Three ways distance matters

Setback from each property line
500 ft under the October ordinance. The December draft doubles it to 1,000 ft.
Notice of scheduled generator tests
Owners within 1,000 ft would get written notice at least 24 hours ahead.
Notice of a development plan
Owners of parcels within half a mile (2,640 ft) of the property boundaries, plus associations in that area registered with Planning and Zoning.

The plan notice is measured from the parcel boundaries. The generator-test clause gives a distance but leaves its starting point unspecified. Ask for the notice map when a project is filed.

Source · p. 8 · p. 9 · p. 11

Who this could affect

Neighbors who rent

A tenant could live across the fence and miss the hearing notice. The draft names parcel owners and registered associations within half a mile as recipients. Renters can check the Planning Commission agenda for the hearing date even if no notice reaches their home.

Source · Proposed neighborhood notice and public hearing, packet p. 11

Households on wells

If a developer proposes private groundwater or would draw surface water for cooling, the draft calls for a study of the supply and effects on existing wells and waterways. A neighbor can check which nearby wells the study considered and what it assumed a dry summer would look like.

Source · Proposed water study requirements, packet p. 10

Directors weighing when to act

In October, André Good and Christina Catsavis favored waiting for stronger protections. Neal Martin and Kevin Settle favored adopting the first rules promptly so projects would face review while the City worked on revisions. December gives readers a chance to compare the added protections with those concerns.

Source · Directors’ October discussion, Talk Business & Politics

What to check next

Signed ordinance, followed by any project file

First check the motion, final wording and effective date. If a project later appears, compare its actual boundaries, notice recipients, utility studies, permit and post-construction sound results with the adopted requirements.

Source · p. 5 · p. 6 · p. 8 · p. 9 · p. 10 · p. 11

If the Board adopts these rules and a project comes forward, follow the property address from the Planning Commission hearing to the Board agenda. Check the Board’s actual motion. Directors could add conditions, send specific questions back to Planning or continue the application to another date.

Source · Proposed development-plan review, packet p. 11