Engineering proposes adding sewer repairs in an adjacent alley to InLiner’s P008 contract. Staff wants the underground work finished before a separate paving project covers the alley. The Board would decide whether to add $536,706.55 and 60 days to the sewer contract.
Proposal history
What earlier documents say
The Clerk records the $6,857,019.47 InLiner Phase I award on May 19. The December memo gives May 7, the date of Engineering’s recommendation.
The alley work would add $536,706.55 and 60 days, bringing the contract to $7,393,726.02 and moving substantial completion from October 6 to December 5, 2027.
Staff found future sewer repairs in alleys scheduled for paving next to InLiner’s work. The City describes its consent-decree program as a way to reduce sanitary sewer overflows. The immediate reason for the change is the sequencing of these two construction jobs.
What would the $536,706.55 buy, and where would the money come from?
Budget reviewers
The largest line on page 85 is $126,902.50 for gravel surface repair. Two major pipe items are $104,400 to replace pipe by bursting the existing line and $103,976 for new 8-inch pipe. The rest covers items including service connections, manholes and other surface repairs. Engineering lists the 2025 sales and use tax bonds as the funding source.
The December memo gives May 7. The Clerk records the Phase I award as resolution R-108-26 on May 19. The change-order sheet lists May 20 as the contract date. Use the Clerk’s action for the vote date.
When would crews need access to the alley and nearby driveways?
Neighbors and businesses
The estimate includes driveway, sidewalk and alley repairs. It gives a deadline for the entire sewer contract. Engineering and the contractor would need to provide the block-by-block work dates and access plan for a resident to plan around a closure.
Engineering labels the added line segment and shows the P008 basin in an inset. The map locates the work. It gives no block-by-block construction dates.
1,044 ft of pipe bursting and 634 ft of new 8-inch pipe
December 5 is the proposed deadline for substantial completion of the entire Phase I sewer contract. The November 25 project sheet lists $756,410.95 in previous payments on that contract.
The City says a sewer service-line replacement can require people to pause flushing, laundry and showers. If this alley work affects your connection, ask for the expected hours and how everyone in the building will be notified, especially anyone who needs a working bathroom throughout the day.
The contractor’s price sheet includes sidewalk, driveway and curb work as well as pipe. Someone using a wheelchair, making a delivery or arranging a pickup can ask which entrance will remain usable while the surface is open.
Signed change order, pay estimates and alley paving schedule
Check the Clerk’s action first. If the Board approves the change, compare the signed price and deadline with the motion. Page 85 gives the quantities and unit prices to check against pay estimates. The contractor’s schedule would show when the alley is ready for paving.
If the change order is signed, ask Engineering for the block-by-block work sequence under project 17-13-C1. The 60-day extension applies to the overall contract. A block’s notice is the place to check when a driveway or sewer connection will be affected.
The sewer proposals cover three different places and decisions. P008 adds construction work, Z003 pays for engineering oversight and Z007 concerns rights to use land. Use the basin and project number when requesting a schedule or invoice.
The engineer told directors that bidding the work in two parts might attract more firms. He also said prices could go either way. Compare the original whole-project estimate with the scope of each phase before drawing conclusions about savings.