Euper Lane water-line change order

The draft resolution would add $52,051 and 63 days to the water-line project. The cost sheet adds to $52,051. One sentence in the engineering memo gives $52,501.

City documents

Proposal excerpt · pp. 189–193 (PDF) · City packet · pp. 189–197 (PDF)

Which amount does the Euper Lane change order support?

Engineering says the contractor found an existing water line outside its recorded position while verifying the crossing. The draft resolution and the itemized change order both specify $52,051. The memo contains a second figure, $52,501, in one sentence.

Proposal history

What earlier documents say

The Board awarded Crawford a $1,125,245 contract in April. The project’s original substantial-completion date was November 28, 2026.

What is proposed for December 1

The draft resolution and itemized change order both say $52,051. One sentence in Engineering’s memo says $52,501. The proposal would add 63 days, moving substantial completion to January 30, 2027.

Questions and evidence

What the records tell us

Why does a project for a 20-inch water main involve moving a 12-inch line?

Neighbors and utility customers

Engineering says crews found an existing 12-inch line in a different position from the plan and field markings. It blocks installation of the 30-inch steel casing for the new main. Page 192 prices 30 feet of replacement 12-inch pipe and two connections to the existing line. Residents looking for interruption dates would need a service notice from the utility.

Source · p. 189 · p. 192 · p. 193

Which deadline would move, and by how much?

Contractors and project managers

The change sheet moves substantial completion from November 28, 2026 to January 30, 2027, adding 63 calendar days. The contractor and engineer signed the packet copy, while the City’s owner-approval lines are blank. Actual completion requires later inspection and acceptance.

Source · p. 191 · p. 193

Which account would pay and how can the work be verified?

Budget reviewers

Engineering identifies 2018 revenue bonds. The change sheet itemizes quantities and unit prices. Compare the approved change and certified pay estimates with those line items before reporting the amount paid.

Source · p. 190 · p. 192 · p. 193

Still to confirm

Which of the two amounts would the Board authorize if it approves the Euper Lane change order?

Residents checking the record

The seven charges and the draft resolution support $52,051. Added to the original $1,125,245, that gives the $1,177,296 total printed on the change order. The other increase in the memo, $52,501, is $450 higher. Check the motion, any amendment and the Mayor’s signed order for the amount the City authorizes.

Source · p. 189 · p. 190 · p. 191 · p. 192 · p. 193

City photograph of boring work at the crossing

Engineering’s October 5 site photograph shows the drill rig used for the crossing. The itemized cost sheet is on page 192 and the revised completion date is on page 193.

City packet · p. 195 (PDF)

The seven charges on the change order

Trench or excavation safety system
$1,900 · 0.19 of a $10,000 lump sum
30-inch steel casing installed by boring
$16,800 · 8 feet at $2,100 per foot
Flowable fill
$3,850 · 17.91 cubic yards at $215 per cubic yard
12-inch ductile iron water pipe in an open trench
$22,440 · 30 feet at $748 per foot
Fittings
$3,111 · 158 pounds at $19.69 per pound
Connections to the existing 12-inch line
$3,000 · 2 connections at $1,500 each
2-inch polyethylene service line
$950 · 30 feet at $31.67 per foot
Total
$52,051

Page 192 lists whole-dollar charges. Three differ by less than a dollar from the displayed quantity times the rate. The printed charges add to $52,051, the amount in the draft resolution on page 191. One sentence of the memo on page 189 says $52,501. Check the motion and signed change order for the amount approved.

Source · p. 189 · p. 191 · p. 192

Who this could affect

Renters and caregivers planning around water service

The dates in the change order are construction milestones. If a shutoff is needed, ask Water Utilities when it would happen and how people in apartments would hear about it. Residents can sign up directly for City water updates by email or phone.

Source · Fort Smith Water Utilities · How to receive updates

Ratepayers following the whole project

In March, Engineering estimated $2 million in 2026 spending for the Euper Lane project. December’s proposed $1,177,296 is the revised construction contract. To compare the two fairly, ask Finance which other costs fall under the project and how much has been paid so far.

Source · March water capital plan · project estimate, p. 75

What to check next

Clerk’s record of the Board action and any signed change order

Check whether the item passed, changed or was deferred. If approved, compare the adopted amount and time extension with the copy signed for the City. Later pay estimates and acceptance records would establish the amount paid and the work completed.

Source · p. 189 · p. 191 · p. 192 · p. 193

If approved, check the signed order for the authorized amount. After the pipe is installed, ask Engineering whether it updated its utility records with the location crews verified in the field. That correction would help the next crew plan work here.

Source · Engineering’s account of the discrepancy · packet p. 189