Would require governing-body approval before a large technology facility, including a data center, connects to the City’s water system directly or through a contract water customer.
What would a large technology customer have to show before connecting to water?
Some facilities could get Fort Smith water through a neighboring city’s pipes. The Board would decide whether a covered facility needs approval before connecting directly to City lines or through a contract water user. The packet names no pending connection.
Proposal history
What earlier documents say
October’s land-use rules require utility-capacity letters. Water Resources had also reported that Barling and Van Buren bought Fort Smith water under special contracts without a purchase maximum.
The draft would require governing-body approval for covered technology facilities to connect directly or through contract water users. Applicants must project average and maximum daily demand and address fire flow. The draft gives no numerical threshold.
Why ask for both average-day use and maximum-day use?
Water customers and firefighters
Average-day use describes the usual load. Maximum-day use shows the projected peak. A fire can require a large flow over a short period, so the draft also asks about fire-flow capacity. At a project review, ask the utility how much flow would remain for firefighting on the projected peak day.
It applies to large-scale technology or digital infrastructure uses, including data centers. It sets no gallons-per-day or floor-area threshold. For a facility outside the named example, ask staff to explain why the proposed use falls within the ordinance.
Would this vote set rates or commit money for an expansion?
Ratepayers and utility managers
This vote would set the approval process. The draft specifies no rate, upgrade budget or share of costs. For a later request, a project cost estimate, service agreement and any proposed City spending would help show who pays.
How could residents compare projected use with actual use?
Watershed users
The draft requires demand forecasts and estimates of effects on groundwater and surface water. It sets no schedule for publishing actual use. If service begins, compare the facility’s forecast and meter totals for the same period. A whole-city water total would also include households and other customers.
Who would approve a connection through Barling or Van Buren?
Barling and Van Buren customers
The draft names both cities and calls for “governing body” approval. It does not identify which governing body would act on an indirect connection or the order of any local approvals. In February, Water Resources reported that neither city’s wholesale contract capped purchases. Ask Fort Smith and the supplying utility to identify who signs off under the applicable agreement.
Read § 25-68(d) in the first section of the draft. One paragraph identifies the covered land uses, the two supply routes and what an applicant must submit.
A direct City line or the line of a contract water user, including Barling and Van Buren.
Describe the demand
Annual, monthly, average-day and maximum-day projections, plus fire-flow capacity and effects on ground and surface water.
Seek a public decision
The draft requires approval by “the governing body.” For a connection through another city, ask which body will hear the request and where its decision will be recorded.
These are application requirements. The two-page packet contains no project demand forecast, available-capacity calculation or measured use.
In September, a damaged main along Highway 45 prompted mandatory conservation south of Zero Street while local storage recovered. For a proposed customer, ask which pipes and storage tanks would serve it, and how nearby homes and fire hydrants would be supplied if that main were out.
Van Buren Municipal Utilities explained in 2024 that its wholesale share should cover storing, treating and transmitting water to Van Buren. For a project needing a larger line, ask which part would serve the applicant and whether any cost would qualify for inclusion in wholesale rates under the agreement.
Final code text and the first covered connection request
Check which uses and approval authority the adopted text covers. For any later application, look for demand and fire-flow estimates and the decision on that connection. Meter readings after service begins could then be compared with the original forecast.
If the ordinance passes, check the published utility code at § 25-68(d). When a facility seeks service, look for an application naming the supplier, its monthly and peak-day forecasts, and a public decision on that connection. The draft leaves the cost of any system upgrade for a later decision.
A future data center inside Fort Smith could need two decisions. Planning reviews the site. A covered connection to Fort Smith water would also go to the Board, including when a contract customer supplies the water.
Director Kevin Settle asked staff to explore a rate four times the existing rate. The December draft asks for Board review of covered connections and sets no new water price.
During a hot, dry spell, the City cited rising irrigation demand and asked households to alternate watering days. It gives a local example of why maximum-day demand matters when reviewing a proposed connection.