Would authorize up to $106,610 for I&S Group to oversee the sewer construction. The resolution allows 480 calendar days. The engineering scope uses a different schedule.
The Board awarded the Z003 sewer construction work to Goodwin & Goodwin on November 2. On December 1 it would decide whether to hire I&S Group to review the contractor’s work and assist City inspectors, for up to $106,610.
Proposal history
What earlier documents say
Goodwin’s negotiated construction term was 390 days. The consultant’s November exhibit assumes 360 construction days plus 90 days before and after construction, yet states a 480-day total.
The separate I&S engineering agreement would run 480 days. It caps fees at $106,610, with $60,380 for administration and $46,230 for observation. City staff would handle daily inspections.
Who would inspect the sewer work and who would accept it?
Residents and utility crews
City Engineering inspectors would handle day-to-day inspection. I&S would make periodic visits and, at the City’s request, fill in for an unavailable inspector for up to five workdays. I&S would review the final work and recommend acceptance. The City would make the decision.
What does the $106,610 engineering fee cover, and when could it change?
Ratepayers
I&S would bill by the hour, up to $106,610 for the work described. The estimate includes expected travel time and mileage. A change beyond the original scope or design could require a newly negotiated fee. If construction runs long, the parties could consider an amendment for extra time and materials. Goodwin & Goodwin’s separate $5,060,015.50 contract covers construction.
The project engineer’s signed selection memo names the three firms considered from qualifications on file with the Clerk. It lists Hawkins-Weir, Halff and I&S and identifies I&S as best qualified. Page 124 sets out I&S’s proposed fee and services.
Which construction schedule underlies the 480-day engineering fee?
Contract managers
The draft resolution allows 480 days. Exhibit A assumes 360 days of construction plus 90 days of engineering work around it, a total of 450. The November construction proposal used 390 days, which would bring the total to 480. Ask Engineering to reconcile the two schedules and identify when a delay could trigger a fee amendment.
The inset places the sewer sub-basin within the city. Engineering describes work on roughly 6,158 feet of mains and 110 manholes. Individual construction dates depend on the contractor’s schedule.
The two allowances add to $106,610. They cover engineering services across the project, including review and inspection support. The City would continue daily inspection.
A resident can report a water or sewer emergency to City System Control at 479-784-2342, 24 hours a day. That gives residents and tenants a direct route for a current problem while the City and consultant oversee construction.
Arkansas publishes reports of sanitary sewer overflows. Compare the incident locations and dates with the Z003 work area when evaluating results. A change in the citywide count alone cannot tell whether repairs in this basin worked.
Executed agreement, inspection logs and monthly invoices
Confirm the service period and fee ceiling in the signed agreement. Match billing to the City’s inspection logs, I&S meeting summaries and observation requests, then check the punch list and the City’s acceptance.
If the agreement is executed, ask Engineering to connect an inspector’s finding, the contractor’s correction and the final acceptance record for the same sewer segment or manhole. Project 25-12-EC1 identifies the engineering contract.
The sewer proposals cover three different places and decisions. P008 adds construction work, Z003 pays for engineering oversight and Z007 concerns rights to use land. Use the basin and project number when requesting a schedule or invoice.
The City’s 2023 assessment lists individual Z003 manholes for repair or relining and identifies others that still needed inspection. Search the report for “Z003” to compare the earlier findings with the work described in the engineering agreement.